Resource assign analysis in the resource graph view in MS Project Pro
Contents:
- The resource graph view in MS Project Pro
- Resource assign analysis in the resource graph view in MS Project Pro
- Resource group assign analysis in the resource graph view in MS Project Pro
- Cost assignment analysis in resource graph view in MS Project Pro
- Chat
The resource graph view in MS Project Pro
MS Project Pro has views in which you can analyze the loading of different types of resources. This view is the "Resource graph" view. Let's make some settings before using it.
Steps to make settings the graph view:
- Open the resource graph.
- Click the "View" item in the top menu.
- You can use the "Group ..." system filter.
- You can crate a new filter by the "RBS" field. (Read more "Creating a custom resource breakdown structure column in MS Project Pro")
- You can crate a new filter by the "Cost type" field. (Read more "Сreating a custom field to describe the cost type in MS Project Pro")
- Set a filter and select the required resource group.
- Set the time period in the "Timescale" field.. (Read more "Timescale in MS Project Pro")

Resource assign analysis in the resource graph view in MS Project Pro
Steps to resource assign analysis in the resource graph view in MS Project Pro:
- Click the "Resource Graph Format" item in the top menu.
- Select the resource in the "Navigate" block.
- Select the graph in the "Graph:" field.
- Peak Units - number of specialists in percent.
- Work - the number of hours of loading resources for the period.
- Overallocation - the number of hours of resource overload for the period.
- Percent Allocation - resource load percentage for the period.
- Remaninig Availability - the number of remaining resource availability in hours.
- Unit Availability - the number of remaining availability of a resource in percent.
- Work Availability - resource availability in hours.

Resource group assign analysis in the resource graph view in MS Project Pro
Steps to set the in the resource graph view in MS Project Pro:
- Click the "Resource Graph Format" item in the top menu.
- Click the "Bar Styles" button.
- You can show or hide various chart elements in the "Show as:" field.
- You can set the color element in the "Color:" field.
- You can set the pattern element in the "Pattern:" field.
- Show the overallocated resources.
- Show the allocated resources.
- Click the "Ok" button.
- If you have used a filter, you will see the resource group loading.

Cost assignment analysis in resource graph view in MS Project Pro
Steps to cost assignment analysis in resource graph view in MS Project Pro:
- Click the "Resource Graph Format" item in the top menu.
- Select the resource in the "Navigate" block.
- Select the graph in the "Graph:" field.
- Cost - resource cost per period.
- Cumulative Cost - cumulative resource costs for each period.

#msprojectpro, #oberemokii, #projectmanagment, #projectresourcemanagement, #monitoringandcontrollingprocess