Leveling resources by increasing duration in MS Project Pro

<< Back

Contents:

  1. Leveling resources by increasing duration in MS Project Pro
  2. Chat


Leveling resources by increasing duration in MS Project Pro

When assigning one resource to several parallel tasks, a resource conflict is possible. If the resource is assigned all its time to each task. We can increase task duration and resolve resource conflict without changing the work. The resource will spend less time per day on each task.

Steps to analyze resource loading by increasing duration in MS Project Pro:

  1. Open the Gantt chart view.
  2. Select the task with a resource conflict.
  3. Click the "Task" item in the top menu.
  4. Click the "Details" button in the "Properties" block. 
  5. Open the resource usage in the button.
  6. Set the daily time period. (Read more "Timescale in MS Project Pro")
  7. Open the time period with a resource conflict.
  8. Click the "Resource Usage Formate" item in the top menu.
  9. Click boxs: "Work" and "Overallocation".

Set the Gantt chart for leveling resources by increasing duration in MS Project Pro

Steps to leveling resources by increasing duration in MS Project Pro:

  1. Click the "View" item in the top menu.
  2. Click the "Sort" button and click the "Sort By ..." item.
  3. Sort by the "WBS" field. (Read nore "Sorting information in a view in MS Project Pro")
  4. Increase the duration of a task with a resource conflict.

Leveling resources by increasing duration in MS Project Pro


#msprojectpro, #oberemokii, #projectmanagment, #projectresourcemanagement, #planningprocess

Leveling resources by increasing duration in MS Project Pro

2023-02-08 11:50:21

Ivan Oberemok

oberemokii@gmail.com

Chat


Chat for registered users only Login