Leveling resources by redistributing resource works in MS Project Pro
Contents:
Leveling resources by redistributing resource works in MS Project Pro
Steps to setting the resource view for leveling resources by redistributing resource works in MS Project Pro:
- Open the resource view.
- Select the resource with a resource conflict.
- Click the "Resource Usage Format" item in the top menu.
- Click boxs: "Work", "Overallocation" and "Remaining Availability"
- Set the daily time period. (Read more "Timescale in MS Project Pro")
- Add columns: "Peak", "Assignment Units", "Start", "Finish", "Baseline Work" and "Work Variance"

Steps to leveling resources by redistributing resource works in MS Project Pro:
- Select first time perion with a resource conflict.
- Change the assignment work to the period so that the overallocation (the "Overalloc." field) is zero.
- Move the rest of the work to the next business day.
- Go to the next period with a resource conflict and repeat the steps

- As a result, you will resolve the resource conflict
- But it is also possible that you will increase the deadlines for the implementation of the project task.