Creating a new plan in MS Project
Contents:
- Creating a new plan in MS Project Pro
- Opening a plan in MS Project Pro
- Saving a plan in MS Project Pro
- Chat
Creating a new plan in MS Project Pro
Steps to creating the blank plan:
- Click the item "File" in the top menu.
- Click the item "New" in the left menu.
- Click button "Blank Project".
Steps to create a plan based on a template:
- Click the item "File" in the top menu.
- Click the item "New" in the left menu.
- Choose the template and click button "Create".

Opening a plan in MS Project Pro
Steps to opening the plan:
- Click the item "File" in the top menu.
- Click the item "Open" in the left menu.
- You can choose a plan with which you have already worked.
- You can also select project location. You can choose different locations to store projects.
- Choose the file in opening location.
- Click the button "Open".

Saving a plan in MS Project
Steps to saving the plan:
- Click the item "File" in the top menu.
- Click the item "Save" in the left menu.
Steps to saving the plan in different location and name:
- Click the item "File" in the top menu.
- Click the item "Save as" in the left menu.
- Choose the location to save the plan
- Choose the location and the name plan in the window "Save as".
- Click the button "Save".