Task mode in MS Project Pro
Contents:
Using task mode in MS Project Pro
You can use the task mode to plan a project when information is lacking. You can add information to the project as you receive it.
Steps to use task mode in MS Project Pro:
- Add the "Task Mode" column.
- Set the "Manually Scheduled" for the tasks.
- Set the information in columns (Duration, Start, Finish).
- For a summary task, you may see a red line if the calculated duration is greater than. If the calculation duration is less than or equal to the duration of the summary task, a cyan line will be displayed.
- Conflicting column values are displayed with a red waveline.

Customize task mode in MS Project Pro
You can set the task mode for project tasks in MS Project Pro.
Steps customize task mode in MS Project Pro:
- Add the "Task Mode" column.
- Set the task mode for the task.
You can set the task mode for a new tasks this project or all projects in MS Project Pro.
Steps customize task mode for a new tasks in MS Project Pro:
- Click the "File" item of the top menu
- Click the "Options" item of the left menu.
- Click the "Schedule" item of the left menu in the "Project Options" window.
- Select the name project ot the "All New Project" item in the "Sheduling options for this project:" block.
- Select the task mode in the "New tasks created:" field.
- Click the "Ok" button.

#msprojectpro, #oberemokii, #projectmanagment, #projectschedulemanagement, #planningprocess