Milestones in MS Project Pro
Contents:
- Using milestones in project schedule in MS Project Pro
- Adding milestones in project schedule in MS Project Pro
- Customize the style of strategic milestones on the gantt chart in MS Project Pro
- Chat
Using milestones in project schedule in MS Project Pro
You can use the milestones in project schedule for describe some events.
- External events that affect the project.
- Project internal events.
Steps to select milestones in project schedule:
- First tool:
- Add the "Milestone" column.
- Click the column menu and select the"Yes" value.
- Second tool:
- Click the "View" item of the top menu.
- Click the "Filter:" field in the "Data" block.
- Select the "Milestone" filter.
Steps to highlight milestones in project schedule:
- Click the "View" item of the top menu.
- Click the "Highlight:" field in the "Data" block.
- Select the "Milestone" filter.
Steps to set milestones on the summary tasks in project schedule:
- Double click the milestone.
- Click the "General" tub.
- Click the "Rollup" box.
- Click the "Ok" button.

Adding milestones in project schedule in MS Project Pro
First tool. Steps to add the milestone in project schedule in MS Project Pro:
- Click the "Task" item of the top menu.
- Click the "Milestone" button in the "Insert" block.
- Enter the milestone name in the "Task Name" field.
Second tool. Steps to add the milestone in project schedule in MS Project Pro:
- Insert the task by clicking the "Insert" keyboard button.
- Enter zero duration in the "Duration" field.
You can set a task as a milestone. This milestone must have work and resources assigned.
First tool. Steps to add a task as a milestone in project schedule in MS Project Pro:
- Add the "Milestone" column.
- Set to "Yes" for the task.
Second tool. Steps to add a task as a milestone in project schedule in MS Project Pro:
- Position the cursor on a task.
- Click the "Information" button in the "Properties" block.
- Click the "Advanced" tub.
- Click the "Mark task as milestone" box.

Customize the style of strategic milestones on the gantt chart in MS Project Pro
You can highlight strategic milestones on a Gantt chart in your schedule.
Steps customize the style of strategic milestones on the gantt chart in MS Project Pro:
- Open the gantt chart.
- Click the "Gantt Chart Format" item of the top menu.
- Click the "Format" button in the "Bar Styles" block.
- Click the "Bar Styles" subitem.
- Scroll to the bottom of the list
- Enter the "Strategic milestone" in the "Name" field.
- Set the strategic milestone style in the "Appearance" field.
- Copy the list of column form the milestone style in the "Show For ... Tasks" filed.
- Add the "Strategic" column in the "Show For ... Tasks" filed.
- Set the "Task Finish" in the "From" column.
- Set the "Task Finish" in the "To" column.
- Click the "Ok" button.