Assigning resources in MS Project Pro
Contents:
- Assigning resousces in table in MS Project
- Assigning resources in window "Task Information" in MS Project
- Assigning resources in window "Assign Resources" in MS Project
- Assigning resources in window "Task details form" in MS Project
- Chat
Assigning resources in table in MS Project
First tool assigning resources in table in MS Project:
- Open "Gantt Chart" in your plan.
- Add the column "Resource Names".
- Choose the resource in the colums "Resource Names".
Assigning resources in window "Task Information" in MS Project
Second tool assigning resources in table in MS Project:
- Click the task twice the mouse.
- Choose the tub "Resources" in the window "Task Information"
- Choose the resources in the field "Resource Name".
- Set the units for each resources in the field "Units".
- Click the button "Ok"
Assigning resources in window "Assign Resources" in MS Project
Third resource assignment tool in a table in MS Project:
- Click the item "Resource" in the top menu.
- Click the item "Assign Resources" in block "Assignments".
- Choose resources in the window "Assign Resources".
- Select the resource and click the button "Assign".
- Enter units for each assigning resources in the field 'Units".
Assigning resources in window "Task details form" in MS Project
Fourth resource assignment tool in a table in MS Project:
- Click the item "Task" in the top menu.
- Click the item "Details" in block "Properties".
- Click the item "Task Form Format" in top menu for window "Task details from".
- Click the item "Work" in block "Details"
- Choose resources in the window "Task details from" in the field "Resource Name".
- Enter units for each assigning resources in the field 'Units".
- Click the button "OK".