Creating the custom columns "Product by % complete" and "Product variance" in MS Project Server
Using the % complete column and the planned number of products you can calculate how much of a task's product can be done. Let's create a column that will calculate this.
Steps to create custom columns: "Product by % complete" and "Product variance" in MS Project Server:
- Open MS Project Server
- Click the "Server Settings" item in the left menu.
- Click the "Enterprise Custom Fields and Lookup Tables" item in the "Enterprise Data" block.
- To create the custom fields, click the "New Field" button.

Steps to create custom columns: "Product by % complete" and "Product variance" in MS Project Server:
- Enter the field name in the "Name" field.
- Enter the field description in the "Description" field.
- Select the "Task" in the "Entity" field.
- Select the "Number" in the "Type" field.
- For the custom column: "Product by % complete":
- Select the Formula in the "Custom Attributes" block.
- Enter the formula: "[Plan product] * [% Complete] / 100".
- For the custom column "Product variance":
- Select the Formula in the "Custom Attributes" block.
- Enter the formula: "[Product by % complete] - [Actual product]".
- To save click the "Save" button.

Using the custom columns "Product by % complete" and "Product variance" in MS Project Server
Steps to add custom columns: "Product by % complete" and "Product variance" in MS Project Server:
- Click the "Server Settings" item in the left menu.
- Click the "Manage Views" item in the "Look and Feel" block.
- Click the "Tasks Schedule" view.
- Add columns: "Plan product","Actual product", "Product by % complete" and "Product variance" in the "Fields" block.
- To save click the "Save" button.
Steps to use custom columns: "Product by % complete" and "Product variance" in MS Project Server:
- Click the "Projects" item in the left menu.
- Select the project and click the project name.
- Click the "TASK" item in the top menu.
- Select the "Tasks Schedule" view in the "View" field in the "Data" block.
- Click the "Edit" button in the "Project" block and select the "In Browse" item.
- Enter data in the "Plan product" and "Actual product" fields.
- To save click the "Save" button.