Using the assignment owner and status manager in MS Project Server
Contents:
- Setting the default assignment owner for a resource in MS Project Server
- Using the assignment owner and status manager in MS Project Server
- Chat
Setting the default assignment owner for a resource in MS Project Server
Steps to set the default assignment owner for a resource in MS Project Server:
- Open MS Project Server.
- Click the "Resources" item in the left menu.
- Click the "RESURCES" item in the top menu.
- Select the resource, click the box near the resource name.
- Click the "Edit" button in the "Resources" block.
- Click the "Browse ..." button in the "Default Assignment Owner:" field,
- Click the user name in the "Pick Resource" window. You can find the first three characters of the username by clicking the "Search" button.
- Click the "OK" button in the "Pick Resource" window.
- To save click the "Save" button.
Steps to set the default assignment owner for resources in MS Project Server:
- Click the "Resources" item in the left menu.
- Select resources, Click the boxs near the resource name.
- Click the "RESOURCES" item in the top menu.
- Click the "Bulk Edit" button in the "Resources" block.
- Click the "Browse ..." button in the "Default Assignment Owner:" field,
- Click the user name in the "Pick Resource" window. You can find the first three characters of the username by clicking the "Search" button.
- Click the "OK" button in the "Pick Resource" window.
- To save click the "Save" button.

Using the assignment owner and status manager in MS Project Pro
You can set up a resource assignment owner on each project task. The assignment owner can report on task completion and resource usage. The state manager can receive the results of the execution of project tasks. By default, the state manager is the project manager.
Steps to set the assignment owner and status manager for resources in MS Project Pro:
- Open MS Project Pro.
- Open the "Task Usage" view.
- Add the "Assigment Owner" column and the "Status Manager" column and.
- Choose the username in these columns.
- Publish your project.
Step to set the assignment owner for the resource in MS Project Pro:
- Open MS Project Pro.
- Open the "Gantt Chart" view.
- Click the task twice the mouse.
- Choose the tub "Resources" in the window "Task Information"
- Choose the assignment owner in the field "Assignment Owner".
- Set the units for each resources in the field "Units".
- Click the button "Ok"

#projectportfoliomanagement, #projectresourcemanagement, #initiatingprocess, #msprojectserver, #oberemokii