Adding the enterprise custom column to assigning responsible persons in MS Project Server
Contents:
- Adding the enterprise lookup table to assigning responsible persons in MS Project Server
- Adding the enterprise custom column to assigning responsible persons in MS Project Server
- Adding the responsible field to the view in MS Project Server
- Chat
Adding the enterprise lookup table to assigning responsible persons in MS Project Server
Responsible for the task is an employee of the company implementing the project. Responsible is a specialist in the subject area. The person in charge determines the list of tasks, their duration, links between other tasks and the necessary resources.
The project manager determines the responsible task. The project manager coordinates with the responsible person all the parameters of the tasks.To assign a responsible person, you need to create a column.
Steps to add the enterprise lookup table to assigning responsible persons in MS Project Server:
- Click the "Server Settings" item in the left menu.
- Click the "Enterprise Custom Fields and Lookup Tables" item in the "Enterprise Data" block.
- To create the lookup table, click the "New Lookup Table" button.
- Enter the "Responsibles" in the "Name" field.
- Select the "Text" in the "Type" field.
- Add vlues to the lookup table:
- Enter the table values in the "Value" column.
- If you want, you can add the description in the "Description" column.
- To save click the "Save" button.

Adding the enterprise custom column to assigning responsible persons in MS Project Server
Steps to add the enterprise custom column to assigning responsible persons in MS Project Server
- Click the "Server Settings" item in the left menu.
- Click the "Enterprise Custom Fields and Lookup Tables" item in the "Enterprise Data" block.
- To create the lookup table, click the "New Feild" button.
- Enter the "Responsible" in the "Name" field. The name must to be unic.
- Select the "Task" in the "Entity" field.
- Select the "Text" in the "Type" field.
- Select the "Lookup Table" in the "Custom Attributes" block.
- Select the lookup table name ("Responsibles").
- If you want to use a default value:
- Click the "Choose a value to use as a default when adding new items" box.
- Select the default value.
- To save click the "Save" button.

Adding the responsible field to the view in MS Project Server
Steps to add the responsible field to the view in MS Project Server:
- Click the "Server Settings" item in the left menu.
- Click the "Manage Views" item in the "Look and Feel" block.
- Click the "Tasks Schedule" view.
- Add the responsible field in the "Fields" block.
- To save click the "Save" button.

#projectportfoliomanagement, #projectresourcemanagement, #planningprocess, #msprojectserver, #oberemokii