Bulk editing enterprise resources in MS Project Server
Contents:
Bulk editing enterprise resources in MS Project Server
Steps to select enterprise resources in MS Project Server:
- Click the "Resources" item in the left menu.
- Click the boxs near the resource name.
- Click the "RESOURCES" item in the top menu.
- Click the "Bulk Edit" button in the "Resources" block.

Steps to bulk editing enterprise resources in MS Project Server:
- If you want to change same field click the box near the field.
- Select the username that will be the timesheet manager for the allocated resources in the "Timesheet Manager::" field. Click the "Browse..." button.
- Select the username that will be the default assignment owner for the allocated resources in the "Default Assignment Owner::" field. Click the "Browse..." button. The assignment owner can enter the fact that the task is completed for resources.
- If you want the project manager to approve all project assignments, select the "Resource requires approval for all project assignments" check box.
- Select the RBS to all resources in the "RBS:" field.
- Select the team to all resources in the "Team Name:" field.
- Select the cost type to all resources in the "Cost Type:" field.
- Select the owner department name to all resources in the "Resource Departments:" field.
- Click the "Save" button.